In a contractor sale, the work-in-progress schedule decides the price. A buyer will rebuild it from the job files, test every percentage-complete estimate against actual cost incurred, and convert any optimism into an earnings adjustment. On a business valued at a multiple of earnings, a single overstated job can cost far more than it ever earned.
Contractors know WIP matters for their bonding company and their bank. Very few realize it is the first thing a buyer takes apart. This guide explains why WIP is the whole ballgame in a contractor sale, why the same estimates drive the tax return under Section 460, the look-back method almost no seller raises, exactly what a buyer tests job by job, how a WIP adjustment becomes a multiplied price adjustment, and the preparation that changes the outcome.
Why Is WIP the Whole Ballgame?
Most businesses recognize revenue when they deliver something. Contractors working on long-term contracts recognize it as the job progresses, based on how far along the work is, which means revenue on the income statement is, in part, an estimate made by management about jobs that are not finished. The estimate has two components: cost incurred to date, which is a fact, and cost to complete, which is a judgment. Percentage complete is usually the first divided by the total of both.
Understate the cost to complete and percentage complete rises, which pulls revenue and profit forward into the current period. Nothing has to be fabricated for this to happen. A project manager who believes the remaining work will go smoothly produces a lower estimate than one who has priced in the change orders still under negotiation and the subcontractor who is behind. That is why a buyer does not accept the WIP schedule. They rebuild it.
Why Is the Estimate Also the Tax Method?
Contractors sometimes treat the WIP schedule as something the bonding company wants. For contractors with long-term contracts subject to Section 460, the same cost-to-complete estimates also drive the federal tax return under the percentage-of-completion method, though important exceptions apply, including home and certain residential construction contracts and qualifying smaller-contractor contracts, and those exception rules were modified for contracts entered into after July 4, 2025. Which side of the line each contract sits on is itself a diligence question.
The Code defines the contracts in question plainly: a long-term contract is any contract for the manufacture, building, installation, or construction of property not completed within the taxable year it is entered into (§460(f)(1)), and under §460(b)(1) the percentage of completion is determined by comparing costs incurred before the close of the year with the estimated total contract costs. Read that with a buyer's eyes: the numerator is documented cost incurred; the denominator is a judgment made by the people running the jobs. The statute does not make the estimate reliable, it just tells you the estimate is the mechanism, and everything downstream of it moves when it moves.
One distinction is worth keeping straight. Financial-statement revenue on these contracts is governed by ASC 606, while the federal tax treatment follows Section 460 or an applicable exception; the same job estimates inform both, but the book and tax amounts can differ materially and are not the same methodology. Even so, when a buyer's rebuild says the cost-to-complete figures were optimistic, they are not only saying earnings were overstated, for contracts on the tax percentage-of-completion method, a version of the same overstatement is sitting in filed returns, which raises the question of what happens when those contracts finally close out.
What Is the Look-Back Method Nobody Raises?
Here is the piece that surprises people, and it is worth understanding before a buyer raises it. Because the tax law lets contractors report income on estimates, it also makes them settle up once the estimates are resolved. When a long-term contract completes, the income reported year by year is recomputed using what the job actually cost, and interest runs on the difference in either direction.
The IRS describes the form directly: Form 8697 figures the interest due or to be refunded under the look-back method of Section 460(b)(2) on certain long-term contracts accounted for under the percentage-of-completion (or percentage-of-completion-capitalized-cost) method. The practical consequence in a sale is straightforward: a contractor with a pattern of front-loaded estimates has been reporting income earlier than it was earned, and look-back interest is the price of that. The form's timing is worth knowing, it is generally filed for the year a covered long-term contract is completed, and again in certain later years when the price or costs are adjusted, not merely because a contract is currently open, and the rules carry several exceptions, including the small-contractor and home/residential carve-outs (and, for contracts entered into after July 4, 2025, the look-back method no longer applies to regular taxable income from residential contracts). A contractor whose covered contracts have been completing without any look-back computation should understand why before a buyer asks. It is also a second piece of evidence about estimate quality: a history of look-back computations that come out close to zero says the estimates were good; a history of consistent adjustments says they were not, and the buyer will price the open jobs accordingly.
What Does the Buyer Actually Test?
The work is methodical and it goes job by job on anything material:
- Cost to complete, against evidence. Not the number in the schedule, but what the job file supports, committed subcontracts, open purchase orders, remaining labor hours, and site reports. A cost-to-complete figure that has not moved in four months on a troubled job is the first thing flagged.
- Historical estimate accuracy. The buyer compares the gross margin estimated at 50% complete against the margin actually achieved on completed jobs. A contractor whose jobs consistently finish below the margin they were carrying has a systemic estimating bias, and that bias is applied to every open job.
- Change order treatment. The single most common finding. Under the revenue rules, an unpriced or disputed change can sometimes be recognized before final written approval where the contractor has enforceable rights and the variable-consideration criteria are satisfied, so buyers scrutinize each material change order for enforceable rights, documented scope, and support for the amount. Revenue that cannot meet those tests gets stripped out or discounted.
- Overbillings and underbillings. A heavily overbilled contractor has collected cash for work not yet performed, which flatters the bank balance and creates an obligation the buyer inherits.
- Job cost coding. Whether costs landed on the right jobs. Miscoding moves profit between jobs and makes the whole schedule unreliable even where the totals are right.
- Job fade analysis. The buyer charts how each job's estimated gross margin moved over its life. A job carried at 22% for eight months that finished at 11% is a fade, and a portfolio with visible fade signals that the current schedule is probably still carrying margin that will not arrive. Fade is the most predictive test a buyer runs, because it is backward-looking and not subject to anyone's opinion about the open jobs.
None of this requires the buyer to distrust you. It is standard scope in a contractor transaction, and a seller who has already done the same work arrives with answers rather than surprises.
Selling a contracting business in the next year or two? The WIP schedule is where the price gets set, and the preparation has to happen before diligence, not during it. We do that rebuild the way a buyer will.
Rebuild your WIP before the buyer does →Overbilled or Underbilled: What Does Each Signal?
| Overbilled | Underbilled | |
|---|---|---|
| What it means | Billed more than earned to date | Earned more than billed to date |
| Balance sheet | Liability | Asset |
| Cash effect | Cash collected in advance | Cash not yet collected |
| What a buyer reads into it | Strong billing discipline, or pulled revenue | Weak billing, or unapproved change orders |
| Risk carried to the buyer | Obligation to perform work already paid for | Collection risk on work already performed |
| Common cause | Front-loaded schedule of values | Change orders not processed |
Table: what overbilled and underbilled positions signal to a buyer, and the risk each carries. TC Advisors CPA, October 2026.
Neither position is inherently good or bad. A modestly overbilled position across a portfolio is normal and often reflects good billing practice; a heavily overbilled position concentrated on a few jobs is a question, because the buyer is acquiring the obligation to finish work whose cash has already been spent. Underbillings get less attention from sellers and more from buyers, because they are the place unapproved change orders hide, and an underbilled balance that has been growing for months is usually a job where the customer relationship has deteriorated.
How Does a WIP Adjustment Become a Price Adjustment?
This is the arithmetic sellers underestimate, and it is worth seeing once.
That leverage is the reason WIP preparation pays for itself many times over, and the reason it has to happen before diligence rather than during it. Once the buyer's number is on the table, you are negotiating against their analysis with your own records. And there is a second hit: the same WIP rebuild feeds the working capital target, because underbillings and overbillings are current balance sheet items. One finding can move both the multiple and the settlement at closing, which we cover in our guide to the working capital peg.
Exhibit A
One WIP adjustment, priced at the multiple
A $420,000 accounting adjustment on a sale negotiated at five times adjusted EBITDA
Show the numbers
| Line | Amount |
|---|---|
| Adjusted EBITDA before diligence | $1,400,000 |
| Adjusted EBITDA after the WIP rebuild | $980,000 |
| Multiple | 5× |
| Value before | $7,000,000 |
| Value after | $4,900,000 |
What Preparation Changes the Outcome?
Everything useful here happens before a buyer exists. Revisit cost to complete on every open job, honestly, and document who revisited it and when, a schedule where estimates visibly move as jobs progress is credible, one where they never move is not. Separate approved change orders from unapproved ones in the records, and test whether revenue on the unapproved ones is supported by enforceable rights, documented scope, and satisfaction of the variable-consideration criteria; where it is not, take that adjustment yourself, in a period before the sale process rather than during diligence.
Run the estimate-accuracy analysis on yourself: take your last twenty completed jobs and compare estimated margin at the halfway point against final margin. That analysis is worth doing even if no sale is planned, because it is the only way to find out whether your estimating is systematically optimistic, and the bias is rarely uniform. It tends to concentrate in one project manager, one customer, or one type of work, and once located it is usually fixable within a couple of quarters. Finally, clean up job cost coding and reconcile the job cost system to the general ledger, because a WIP schedule that does not tie to the ledger is the fastest way to lose a buyer's confidence in every other number. And raise the transaction with your surety and lender earlier than feels comfortable, because bonding capacity and change-of-control provisions both take time and can affect whether the deal works at all.
Frequently Asked Questions
Nick Termine, CPA
Because in a contracting business, reported profit depends on management estimates about unfinished jobs. Contractors on long-term contracts recognize revenue as the job progresses, based on how far along the work is, and the percentage complete rests on a cost-to-complete figure that is a judgment, not a fact. That makes the work-in-progress schedule the largest judgment on the financial statements and the easiest place for earnings to be overstated without anyone intending it. A buyer rebuilds the schedule from the job files, tests every estimate against actual cost incurred, and converts any optimism into an earnings adjustment. On a business valued at a multiple of earnings, that adjustment gets multiplied.
Stephen Calvo, CPA
Revenue recognized on change orders the customer has not approved, closely followed by cost-to-complete estimates that have not been revisited since the job started. Change orders are the single most common finding, and the test is more precise than approved versus unapproved: under the revenue rules, an unpriced or disputed change can sometimes be recognized before final written approval where the contractor has enforceable rights and the variable-consideration criteria are met, so buyers scrutinize each material change order for exactly that. Recognized revenue that cannot meet those tests gets stripped out or discounted heavily, and it flows straight into the earnings adjustment.
Nick Termine, CPA
Modest overbilling across a portfolio is normal and often reflects good billing practice. Heavy overbilling concentrated on a few jobs raises a real question, because the buyer is acquiring the obligation to complete work whose cash has already been collected and spent. Billings in excess of costs and estimated earnings is a liability; costs and estimated earnings in excess of billings is an asset. Buyers actually pay closer attention to underbillings, because that is where unapproved change orders hide, and an underbilled balance that has been growing for months is usually a job where the customer relationship has deteriorated. Neither position is inherently good or bad; the concentration and the trend are what a buyer reads.
Stephen Calvo, CPA
A year is comfortable, and two is better, because it lets you take any needed adjustments in a period that is not the period being sold. Everything useful here happens before a buyer exists: revisit cost to complete on every open job and document who revisited it and when, separate approved from unapproved change orders and test whether revenue on the unapproved ones is actually supported, and run the estimate-accuracy analysis on your last twenty completed jobs to find any systematic bias. Taking an adjustment yourself, in a clean prior period, is far better than having a buyer take it during diligence and multiply it into the price.
Nick Termine, CPA
Fade is the gradual decline of a job's estimated gross margin over its life, a job carried at 22% for eight months that finishes at 11%. Buyers chart it across your completed jobs because it is historical and therefore not a matter of anyone's opinion about the open work. Visible fade tells the buyer that the current schedule is probably still carrying margin that will not arrive, so they discount the open jobs accordingly. It is the single most predictive piece of diagnostic work a buyer does, precisely because it is backward-looking. A contractor who runs the same analysis on themselves first arrives at diligence with an explanation rather than a surprise.
Stephen Calvo, CPA
Understand when it applies before you worry. Form 8697 figures the interest due or refunded under the Section 460(b)(2) look-back method, and it is generally filed for the year a covered long-term contract is completed, and in certain later adjustment years, not simply because contracts are open. Exceptions cover many smaller and residential contractors, and for contracts entered into after July 4, 2025 the rules changed further, including that the look-back method no longer applies to regular taxable income from residential contracts. If your covered contracts have been completing with no look-back computation, raise it with your accountant now rather than during diligence. It is a computation, not a penalty, and it can run in your favor as easily as against you.
Nick Termine, CPA
Talk to your surety earlier than feels natural. Bonding capacity depends on the contractor's balance sheet, its track record, and often on personal indemnities from the owner, so a change of ownership is a change of everything the surety underwrote. Where bonded work is material, the surety's position on the buyer is part of whether the deal works at all, because a business that cannot bond is a different business. The lender is the other party to raise early: equipment finance and lines of credit frequently carry change-of-control provisions that are usually solvable and occasionally not, and either way they take time. Neither is a reason not to sell; both are reasons to start those conversations sooner.
Work With TC Advisors
If you are thinking about selling a contracting business, three things this quarter will change the price more than anything else you could do: revisit cost to complete on every open job and document it; split approved from unapproved change orders and make sure revenue on the unapproved ones is supported by enforceable rights rather than assumed; and run the estimate-accuracy analysis on your last twenty completed jobs so you know whether there is a bias before a buyer finds it. We do this through due diligence and transaction advisory and support contractors year-round, and you work directly with a partner. Related reading: the working capital peg and the thirteen-week cash flow model.
Schedule a consultation →- Cornell Legal Information Institute, IRC §460, special rules for long-term contracts
- Internal Revenue Service, Instructions for Form 8697, look-back method for completed long-term contracts
- Internal Revenue Service, About Form 8697, Interest Computation Under the Look-Back Method
Related: The Working Capital Peg and The Thirteen-Week Cash Flow Model.